Every successful project must have a checklist of activities. Please review our version off EEM checklist:
| EEM Step: | EEM ACTIVITY | |||
| 1 | EEM Project Planning & Definition | |||
| 1a | Project Brief/Charter Evaluation | |||
| Fully accepted Project Brief or Contract | ||||
| Set-up first EEM time-table | ||||
| 1b | Project Type Recognition | |||
| Fully Understanding and documentation of the Critical, Success factors / Stakeholders, KPI’s / Deadlines | ||||
| Set the framework of Quality, Timing, Cost and Risk of the Project | ||||
| 1c | Set-up EEM Team | |||
| Realistic / Fully accepted EEM time table by team | ||||
| Project capability 4M | ||||
| Project Planning & control (MS project plan) | ||||
| EEM planning workshop | ||||
| 2 | Conceptual Engineering | |||
| 2a | MP info Collection (on existing & new equipment) | |||
| MP info sheet filled out with: Information (P,Q,C,D,S,E&M), Structurized / prioritized so it can be used to determine future losses/problems in the NEW concept | ||||
| Define machine/ process sub functions (Ex. 1st drafts) | ||||
| Previous Project Documentation = find external examples | ||||
| Commissioning Reports | ||||
| FMEA’s | ||||
| Standard Operation Procedures (SOP), | ||||
| Change over procedures | ||||
| Loss analysis (OEE, Waste) = loss study | ||||
| Skill Matrix | ||||
| Maintenance Records | ||||
| EM (PM) Procedures, Maintenance Calendar | ||||
| Sparepart Consumption | ||||
| Quality Reports | ||||
| QC procedures | ||||
| Consumer Complaints / incident | ||||
| Hygienic design | ||||
| Current Major Losses | ||||
| Improvement Records (training needs) | ||||
| Cleaning/Lubrication/Inspection Standards | ||||
| One Point Lessons | ||||
| Training Procedures | ||||
| Running Costs | ||||
| Safety Records | ||||
| Safety Risk Assessments | ||||
| Ergonomic Information | ||||
| Machine concepts identified (required machine functions defined) | ||||
| 2b | Define Possible Concepts | |||
| visit suppliers & gather their MP Information, Organize a meeting to Define the Possible Concept (Considering P,Q,C,D,S, E & M incl. hygiene) | ||||
| Few machine and/or manufacturing concepts id (and respective potential preferred suppliers) | ||||
| 3 | Preliminary Engineering | |||
| 3a | Utilities Feasibility | |||
| Feasibility study + revision/alteration of the possible concept = utilities study | ||||
| Check if Quantity and Quality of the Utilities (energie, steam, air, etc.) are sufficient for the different concept (defined at step 2) | ||||
| Check re-use / re-cover energie/waste | ||||
| Update plan | ||||
| 3b | Layout Feasibility | |||
| Feasibility study + revision/alteration of the possible concept = layout study | ||||
| ensuring the GMP standards and hygienic requirements (design, CIP, materials) are applied | ||||
| Process Stability (length of transport-belts, movement of products) | ||||
| Show configuration options (and limitations) | ||||
| Show Process Control options (and limitations) | ||||
| Show ergonomic interface options (and limitations) | ||||
| input on: Operability, Maintainability,Cleanability, Safety Exits, Packaging Material Transport, Transport Belts, Utilities Connected | ||||
| Give input how CHANGE OVERS are easy to do | ||||
| Calculate resources (operators etc) needed | ||||
| Input on: doing Effective Maintenance: Inspections , Overhauls , check if Inspections , Overhauls , check if Removal of Equipment (Parts) is easy, Enough Utilities nearby to do Maintenance (Electricity, compressed air, water, light, etc) | ||||
| Input on: Cross Contamination (micro, allergens), Cleanability, Temperature (Product), Fall in bodies, Open Shelf Life, GMP standards are applied, Easy to Inspect (Quality Check Points), Stand times & temperatures (for microbiological issues) relevant for (intermediate) product, Hygiene requirements (incl CIP, Equipment, materials). | ||||
| Safety Exits, Safety Aspects (hot parts /surfaces, sharp corners, easy to reach /access the equipment). Safe Supply of material (forklift truck transport etc), Environmental Issues (Smoke, Cleaning, Liquids, Health Issues (Smoke, Noise, Moisture), Ergonomic Assessment (walk distances, lifting material etc) | ||||
| 3c | Evaluation of Concepts (Quality, timing, cost, Risk) | |||
| Concept Evaluation (PUGH) | ||||
| Risk Assessment (RQS) between team & supplier | ||||
| CapProp – Write the CapProp on technical aspects, incl. Start-up curve, planning, commissioning costs, training plan/costs | ||||
| Nominate favorite Lay-out | ||||
| Start equipment FMEA (on P,Q,C,D,E,S,E&M) (to solve losses in early stage) (system,process, machine) | ||||
| initiate SIMAS | ||||
| 3d | Supplier Selection & Place order | |||
| User Requirements (incl. FAT) | ||||
| Tender | ||||
| Supplier Evaluation (PUGH/NPI criteria) | ||||
| Risk Assessment (RQS together with Supplier) & action plans agreed | ||||
| Prize negotiation (together with NPI) | ||||
| Order (Contract) | ||||
| Approval on User Requirement Spec’s / Payment timings and conditions | ||||
| Agree all details on FAT, EEM Attributes, early operator involvement, user interfaces, control interfaces, etc. | ||||
| Revise plan | ||||
| Optimal concept & suppliers selected | ||||
| 1st Capital proposal | ||||
| 4 | Detail Engineering | |||
| 4a | Detailed Engineering & Design review | |||
| MP workshops with key suppliers | ||||
| dHACCP study | ||||
| Check/optimize: Hygienic Design / SHE / Operability / Ergonomics/ Operability/ Maintainability / | ||||
| Maintainability / Cleanability Review | ||||
| Check detailed drawings on EEM attributes (update design & apply FMEA’s) | ||||
| Use or set-up a “Design Review Checklist” | ||||
| Tagging exercise on similar equipment | ||||
| CAPEX approval | ||||
| Detail design | ||||
| Action lists MP workshop | ||||
| 5 | Procurement & Construction | |||
| 5a | Equipment Fabrication | |||
| Learnings for operators/maintenance (review during building early op involvement, be flexible on relative small changes to further optimize operability, maintainability, cleanability) | ||||
| Before order: establish KPI’s (OEE, rework, CO times…), protocols to be use, agree on FAT conditions, link w project deliverables, | ||||
| Equipment (at AM step 3/4 including cleaning & lubrication Stds) | ||||
| Check: Safety standards, Ergonomic & Environmental aspects | ||||
| 5b | Pre-Fat and FAT at supplier | |||
| Org pre-FAT visit, check status of equip, performed & evaluate FAT, FAT checklist filled out (% accepted) | ||||
| SNAG list (with completion dates / resp) | ||||
| re-fined Training Program | ||||
| finetune forcast & distribute Adjusted (forecasted) Start-up Curve | ||||
| Accept Delivery / Payment agreed to Contract | ||||
| Capture Learnings about Equipment Maintenance | ||||
| 5c | Construction | |||
| Safety Toolbox meeting | ||||
| Agreed Construction Plan (plan & lead construction, instruct contractors on SHE/ GMP/ TPM) Milestones | ||||
| Milestones details (checklist for each milestone) | ||||
| Food safety measures | ||||
| Work Permits | ||||
| Safe behaviour (audits) | ||||
| Update P&ID’s Utilities, Drawing of Buildings, asset list, | ||||
| Develop/review: AM, PM, CO standards (suppliers, & operation) | ||||
| 5d | FAT | |||
| verify: safety stdrs, safety performance | ||||
| verify: Layout, CO requirements, equipment performance, overall equipment performance, | ||||
| verify Documentation (operational stds, manuals, controls, electrical guides) | ||||
| Customer service: service agreement, training and capacitating process | ||||
| Action plan: review and finalize action plan | ||||
| Material for initial flow control workshop | ||||
| 6 | Equipment Installation and Commissioning | |||
| 6a | Equipment Installation | |||
| Safety Toolbox meeting | ||||
| Meeting calendar: w contractors team for week update, include weekly milestones | ||||
| Include contractors on SAFETY routine: dialogues, meetings, events, safety inspections (BBS approach) | ||||
| Work Permits / Safe behaviour (audits) | ||||
| Check Equipment after Delivery (checklist) | ||||
| Agreed Installation and commissioning plan (monitor & lead installation work against Spec/ Lay out) | ||||
| Food safety measures | ||||
| Learnings for operators/maintenance, start 5S, use operability checklist | ||||
| Check all FAT corrective actions are done, check hygiene design aspects of installation | ||||
| Actividades de fin de semana: create a routine 30 min meeting on Friday’s, agree on work, resources required, utilities needed, cafeteria or health care | ||||
| Create calendar for audits on: eng actions, eem actions, Q of installation, 5S, Hygiene | ||||
| Assigned a person to maintain inventory counts also allocate a temp warehouse area for equipment | ||||
| 6b | SAT (site acceptance test) | |||
| Safety go/go/go checks: electrical circuits, safety circuits, safety guards, mechanical mountings, installation of valves (air to open air to close), connection of pipes, … | ||||
| same requirements as FAT | ||||
| Operational documents ready (SOP’s, OPL’s, EM, checksheets) | ||||
| 6c | Equipment Test Run (Dry) | |||
| Agreed/plan /lead Equipment Test Run (Dry) Plan | ||||
| Hardware Functionality Check ( Speed, Temp, safety, etc) | ||||
| Back-up of software settings | ||||
| Locked Hardware Settings | ||||
| Learnings for operators/maintenance | ||||
| Train operators (continue) and deliver all documentation | ||||
| Make / revise maintenance proposal, ensure Critical spare parts are available. Assigned | ||||
| check safety proximity switches + procedures | ||||
| check individual equipment + the interfaces w other equip / transport belts | ||||
| 6d | Product Commissioning (Wet) | |||
| Agreed commissioning plan, organize teams, participate on commissioning | ||||
| Organize resources / workflow / make resource plan for commissioning | ||||
| Revised product and process specs | ||||
| Optimisation to KPI targets (Waste, Manning, etc) | ||||
| Processing Window Defined | ||||
| Fine tuned hardware settings (especially the ones depending on product) | ||||
| Fine tuned software settings + back-up | ||||
| Final SNAG list | ||||
| finalize & distribute AM step 3 Cleaning Standard | ||||
| Generally with water, full protocol to be defined, look for leakers | ||||
| Train operators (continue) and deliver all documentation | ||||
| 6e | Product run and qualification | |||
| Action plan review | ||||
| Ramp up losses identified and prioritised | ||||
| Launch Monitoring Plan, TISI | ||||
| 6f | Initial flow planning | |||
| review plan and flow | ||||
| EEM Initial Flow control Workshop | ||||
| 7 | Start-up Production & Hand over | |||
| 7a | Start-up Production | |||
| Agreed, document & distribute Start-up protocol. Perform Start – up | ||||
| Use ramp up plan and stakeholders expectations | ||||
| Measured / Visualised Performance (check & document product/process performance) (incl start up curve) | ||||
| Ramp measured by Innovation Ramp up KPI | ||||
| Maintenance to participate on start -up and, make necessary adjustments & monitor usage of spare parts | ||||
| Continuous improvement programme: Clear Actions/Speedy kaizens on Problems (act on GAPs between Actual Results vs Targets) | ||||
| Inform other team members about problems occured | ||||
| Intensive Checks on Quality,Safety, Equipm (intensive line inspections) | ||||
| Ensure Quality / Consumer Safety KPIs are met, Ensure CCPs / QCPs are under control | ||||
| Apply Positive Release Principle | ||||
| Review Running Costs | ||||
| Review Initial Project Costs | ||||
| Plan and act on First production | ||||
| TISI | ||||
| Revised Standards | ||||
| 7b | Hand Over | |||
| Make Project Summary (check user requirements) | ||||
| Hand over Document transfer pack for other sites | ||||
| Transfer pack for other sites | ||||
| All Targets achieved | ||||
| All problems solved | ||||
| Officially Agree on Hand-over | ||||
| 8 | Review | |||
| Review on: Briefing , KPI’s & User requirements | ||||
| Post project review against project brief | ||||
| Knowledge Reported (MP info) (review OEE, problems, breakdowns & prod KPI’s) | ||||
| EEM process Review / Improvements mapped | ||||
| Feedback to Team members incl. SU MT, celebrate success | ||||
| Learnings & recommendations for future projects (including overall TPM performance) | ||||